Project Update
WPP acquired 167 rai landfill for 30 years in Thalang Sub-district, Tayang District, Phetchaburi Province in October 2014 and officially registered land rental contract with Land Department. This landfill has been operated for nearly ten years, with the estimated waste reserve of more than 250,000 tons.
WPP signed Power Purchase Agreement under the adder program (PPA) with PEA in August 2014 and also acquired Factory License (Ror Ngor 4) in October 2015. Since 2014 WPP has developed the existing landfill and facilities to solve environmental issue concerned by local people.

Landfill before WPP took over in 2014


Groundbreaking Ceremony on June 25th, 2016 (พิธีวางศิลาฤกษ์) – By Ministry of Interior


Groundbreaking Ceremony on January 31st, 2017 (พิธียกเสาเอก) – By Shareholders


Construction Progress as of October 31st, 2017

Fuel Pit


Tipping Hall Boiler Island


Turbine Hall Water Reservoir


Waste Water Treatment Plant